Rivian updates on the R2 launch, sharing progress on facility expansion in Normal, Illinois. The company announces a new 1.1 million sq. ft. building and increased annual capacity to 215,000 units. Rivian remains on track to begin R2 deliveries in 2026.

Read this email as text

We’re expanding our facilities in Normal

Here’s what that means for R2.

Since being revealed to the world in March 2024, we’ve been working tirelessly to prepare for the launch of R2, starting with construction of a major expansion to our existing plant in Normal, Illinois.

This includes a new 1.1 million sq. ft. building to house the assembly operations and body shop for R2. Despite the freezing Illinois winter, exterior work will wrap up in Q2 2025, and our planned annual capacity will increase to 215,000 units across our vehicle lines when the expansion is complete.

Thanks to this rapid progress, we’re proud to share that we will launch R2 out of our plant in Normal — helping us reduce capital costs and stay on track to begin R2 deliveries as planned in 2026.

Q&A with Tony Sanger

VP of Production Facilities

How close are we to the start of production?

“...[We] should be ramped and producing salable vehicles in the first half of next year.”

What are we doing to speed the build along?

“Prefabrication was the key to [our] accelerated schedule and delivery of the buildings...”

Where are we in the facilities construction phase for R2 in Normal?

Archived for reference and commentary. Rivian, its logos and content are the property of their respective owners; Inbox Archive claims no affiliation and has disabled all links. If you own this content and would like it removed, get in touch.

Similar campaigns from other brands

Different brands running the same play. Compare any of them side by side.

Slate Auto

Fresh prototype builds, comin’ in hot.

Compare →
Scout Motors

Our Factory in Motion

Compare →
Tesla

Announcing Master Plan Part IV

Compare →